Touch Time
Touch time is the time a person or machine is actually working on one unit — the minutes the hinge is in the press, or the minutes an analyst is editing a claim. It is almost always a small slice of lead time.
The rest is waiting, moving, batching, and setup. On a value-stream map, compare touch time (or process time) with the calendar time from start to finish so you can see where improvement will actually shorten delivery.
Touch time, cycle time, and lead time
These three terms get mixed together, even in good plants. Use them this way on a project:
- Touch time (also called process time or value-added time when the work really changes the product): the clock time the unit is being worked on. Add the station times to get total touch time.
- Cycle time is best used as the interval between successive completed units at a process — how often the process can produce. A station that finishes a unit every 90 seconds has a 90-second cycle time, whether the hands-on work was 50 seconds or 90.
- Lead time (throughput time) is the elapsed time from when a unit enters the stream until it is done, including every queue.
Some study guides use “cycle time” as a synonym for process time at a station. If a question does that, read the units and the figure. In Lean, the useful contrast is still the same: work time versus waiting time.
How to measure it
- Stand at the station and time several units from the start of value-adding work to the end. Ignore time the unit spends in a pile next to the machine.
- Record setup, walk, inspect, and fetch separately so they do not inflate touch time.
- Add the station times for a complete unit. That sum is total touch time.
- Compare it with lead time from a value-stream map and with the WIP sitting between stations.
Little’s Law ties the picture together: lead time ≈ WIP ÷ throughput. If touch time is nine minutes and lead time is days, the WIP and the queues, not the operators, are carrying the delay. Track all three with the core Lean metrics.
What to do with a large gap
When touch time is a tiny fraction of lead time, do not start by speeding up the work itself. First:
- Cap and reduce WIP so queues cannot grow without a decision.
- Cut batch sizes and waiting for a “full” cart.
- Move inspection and information closer to the work so units do not sit for a sign-off.
- Only then look at the touch itself — standard work, work instructions, and motion waste — if the station is the constraint.
On Northriver’s hinge line, about 9.4 minutes of processing inside a 7.5-day lead time means more than 99% of the customer’s wait is not touch time. A SMED project on a non-constraint press would not move the delivery date. Clearing the racks in front of assembly would.
Exam notes
Expect items that contrast value-added time with lead time, or that ask which metric you would use to show that most delay is queue time. If a problem gives both process time and wait time, add only the process times for touch time, and add both for lead time.
Frequently asked questions
Is touch time always value-added?
Not automatically. Rework is touch, but it is not value from the customer’s point of view. When you map a stream, separate genuine processing from rework and unnecessary inspection.
Should I include machine automatic time?
Yes, if the unit is being changed by the machine. Do not include the time the unit waits for the next cycle or for a batch to finish.
See also: work in progress (WIP), value-stream mapping, and Lean Six Sigma metrics.
Related line-balancing and flow topics in this guide: work in queue, the theory of constraints, Yamazumi charts, and production line balancing.